01559192562 01030503551 01555441359 0572060545 info@emcegy.net 315/34 13 ST, Abu Al-Kheir, New Damietta, Egypt
Factories, Warehouses & Cold Storage Sector Polyurethane Foam System

Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory

6th of October City, Giza, Egypt
16 Nov 2022
El Anany Group

**Insulation and surface treatment were completed for 3,940 m² of metal roofing at El-Warda Tea Factory – El-Anany Group, using polyurethane foam to ensure effective insulation, surface protection, and extended service life.**

Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 1
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 2
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 3
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 4
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 5
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 6
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 7
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 8
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 9
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 10
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 11
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 12
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 13
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 14
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 15
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 16
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 17
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 18
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 19
Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory 20
1 / 20

Integrated Metal Roof Restoration & Insulation – El Warda Tea Factory

EMC carried out the rehabilitation and insulation of the metal roofs at El Warda Tea Factory, El Anany Group, in 6th of October City, covering a total area of 3,940 m². The project focused on resolving existing roof defects and installing an integrated polyurethane foam system to provide effective thermal and waterproof insulation while protecting the metal roof against moisture, rainfall, and weather exposure.

Scope of Work

  • Cutting and removing excess metal sheet sections and preparing the roof for treatment.
  • Bending metal sheet edges into the rainwater drainage channels to prepare for a continuous insulation layer between the roof sheets and drainage system.
  • Thorough sanding of affected areas to remove corrosion and prepare the metal surface.
  • Complete cleaning of the roof surface.
  • Additional sanding to remove excess material and hardened debris where required.
  • Cleaning and preparation of rainwater drainage channels.
  • Covering large openings and holes with metal sheet patches and securely fixing them to eliminate movement beneath the insulation system.
  • Securing junctions between the metal sheets and skylight openings using reinforced duct tape to minimize movement between adjoining elements.
  • Treating corroded areas with a zinc phosphate-based coating to limit further corrosion.
  • Reinforcing treated areas with duct tape and applying an additional anti-corrosion protective coating.
  • Treating rainwater drainage channels to protect them against corrosion.
  • Treating skylight edges with geotextile-reinforced acrylic coating for additional protection and stabilization before polyurethane foam application.
  • Applying polyurethane foam in three layers, 1 cm per layer, to achieve a final thickness of 3 cm (±5 mm).
  • Applying the first acrylic protective coat manually to ensure detailed surface coverage.
  • Spray-applying the second acrylic protective coat to achieve complete and uniform coverage and protect the polyurethane foam against UV radiation and weather exposure.

Case Study

The Challenge

The metal roof suffered from misaligned sheets, large openings and holes that allowed rainwater to leak into the factory, as well as widespread corrosion affecting metal sheets and structural beams. Several areas also required stabilization and detailed treatment before the insulation system could be applied.

The Solution

A comprehensive roof rehabilitation process was carried out, including metal sheet adjustment, hole patching, stabilization of loose sections, zinc phosphate corrosion treatment, and rehabilitation of drainage channels and skylight junctions. The roof was then insulated with three layers of polyurethane foam to a total thickness of 3 cm (±5 mm) and finished with two acrylic protective coats.

The Result

The 3,940 m² metal roof was transformed into a continuous thermal and waterproof insulation system, with major leakage points and vulnerable roof areas properly treated. The polyurethane foam system helps reduce heat transfer through the roof and improve the factory's thermal performance, while the acrylic coating provides additional protection against UV radiation and weather exposure and enhances the system's waterproofing performance.

Project Videos

Thermal and Waterproof Insulation Using Polyurethane Foam System for El Warda Tea Factory in 6th of October City