Completion of Thermal and Waterproof Insulation Works at Warehouse F – Arma Soap & Chemicals, 10th of Ramadan City
EMC has announced the successful completion of thermal and waterproof insulation works for the metal roofing system using polyurethane foam at Warehouse F, owned by Arma Soap & Chemicals, in 10th of Ramadan City, covering a total area of 12,192 m².
The project was carried out to provide an integrated insulation solution for metal roofs, aimed at reducing heat transfer, enhancing protection against rainwater leakage and weather conditions, maintaining facility efficiency, and extending the service life of the roofing system.
Scope of Work
The project included several stages of surface preparation, treatment, and insulation, as follows:
-
Site Inspection and Technical Assessment: Inspecting the roof and evaluating its technical condition to determine surface preparation and insulation requirements.
-
Metal Sheet Fastening: Riveting and securing the required metal roofing sheets to ensure proper surface preparation.
-
Surface Cleaning: Thoroughly washing and cleaning the entire roof surface to remove dust, dirt, and contaminants.
-
Drainage Channel Treatment: Inspecting and cleaning rainwater drainage channels to ensure efficient water drainage.
-
Drainage Channel Waterproofing: Applying a fiberglass-reinforced blister waterproofing system to the rainwater drainage channels.
-
Drainage Channel Protective Coating: Applying a Coat PU protective layer to the drainage channels.
-
Polyurethane Foam Insulation: Spraying polyurethane foam at a thickness of 3 cm ± 5 mm to provide thermal and waterproof insulation for the metal roofing system.
-
Final Protective Coating: Applying an acrylic protective coating to protect the insulation system against weather conditions.
Project Details
-
Project Name: Warehouse F – Arma Soap & Chemicals
-
Location: 10th of Ramadan City, Egypt
-
Total Area: 12,192 m²
-
Roof Type: Metal Roofing
-
Insulation System: Polyurethane Foam
-
Foam Thickness: 3 cm ± 5 mm
-
Final Protective Coating: Acrylic
-
Completion Date: January 9, 2026